Saturday, February 14, 2009

BMW Dealership

ABW Construction recently had the opportunity to demonstrate to Foushee and Associates (one of Seattle's leading General Contractors) the amazing power of the SuperCap System and the Power of the Pump Truck. Floor tolerance specification for the 14,000 s/f showroom was stringent. Time was of the essence and we were asked to help engineer a solution. We surveyed the floor to determine the exact quantity of material necessary to achieve the ceramic tile specification (1/8" in 10'). Once Foushee, Western Tile and Marble and ABW agreed to the plan, we mobilized. In just two days we cleaned the substrate, set grade with level pegs, applied primer, and poured an average of 3/4" of SuperCap 5000. The first day was spent setting elevation pins and priming. On the second day, the power of the Pump Truck allowed us to pour all 85,000lbs of material in just 3.5 hours! Our impact on the job was minimal. Nothing went into the building accept 1 hose and 4 men. The results were outstanding.